week 10_

November 22, 2010 § Leave a comment

Straightening walls, pre-wiring and plumbing, fitting insulation

Advertisements

week 9_

November 21, 2010 § Leave a comment

Installing cedar sliding doors and glazing them, fixing poplar ceiling plywood

This slideshow requires JavaScript.

week 8_

November 21, 2010 § Leave a comment

Fixing aluminium joinery, flashings, and finishing exterior battens

week 7_

November 21, 2010 § Leave a comment

Pre-cutting and oiling decking, pre-sealing interior ply

 

 

week six_

November 21, 2010 § Leave a comment

fixing roofing on and finishing off cladding

week five_

November 18, 2010 § Leave a comment

Roof goes up; ‘sandwich’ style consisting of metal profile on top, flat metal on the bottom and 300mm of polystyrene in between.

 

week four_

September 21, 2010 § Leave a comment

Half of the team working in the workshop this week_ priming cladding battens, crafting external sliding doors etc.

Half of the team working out in the elements_ fixing external cladding; a “shadow clad plywood – band sawn”

  • follow us on twitter_

    • Come to the Grad show 24th Nov to see the finished product! 8 years ago
    • Almost done now, got a deck on one side and finishing things off inside for the grad show! 8 years ago
    • Got two of the six pieces of roof fixed on thursday. Starting to look more like a house now. 8 years ago
    • Roof is going on today!!! It's here right now so we gotta get it on! 8 years ago
    • Roof is supposed to be going on today but due to wind will most definitely not! 8 years ago
    • Roof will be going up on Thursday, weather dependent, then we will get a better idea of the finished product 8 years ago
    • Paris Hilton of the day yesterday was Whitney! She took a dwang out to move it and put it back in the same place. Good one whit! 8 years ago
    • Hope to have the roof on by next week. 8 years ago
    • We have now got all the wall framing up and are working on cladding with ply and battens 8 years ago
    • We're building - Monday, Tuesday and Thursday. Feel free to ask us questions; we're the ones wearing tool belts 8 years ago
    • Come down to the building site - next to the work shop. Check out what we have done so far! 8 years ago
    • #ecv10 view progress of the construction of the bach at http://onemanabach.wordpresss.com 8 years ago
    • we are up and running_ stay tuned to keep track of our construction progress 8 years ago
    • Our Wordpress blog is almost on the go, stay tunned for updates on the building of the bach at Unitec! 8 years ago
  • creators_

    Lyn Richardson
    Matthew Roberts
    Miro Wang
    _3rd yr Bachelor of Architectural Studies students - Unitec_